Category | Region (Lead Organization) | Hydrogen Production Scale | Project Period | Note | |
---|---|---|---|---|---|
Small Scale | 2019 |
Gyeongnam Changwon (Changwon Industry Promotion Agency) |
1 t/day (460 Nm3/h) | Jun. 1, 2019 - Mar. 31, 2021 (22 months) | Construction Completed |
Gangwon Samcheok (Gangwon Technopark) |
1.3 t/day (600 Nm3/h) | Jun. 1, 2019 - Mar. 31, 2022 (34 months) | Construction Completed | ||
Gyeonggi Pyeongtaek (Gyeonggi Economic Science Promotion Agency) |
7.1 t/day (3,300 Nm3/h) | Dec. 1, 2019 - Apr. 30, 2022 (29 months) | Construction Completed | ||
2020 |
Daejeon (Daejeon Urban Corporation) |
1.3 t/day (600 Nm3/h) | May 1, 2020 - Feb. 28, 2023 (34 months) | Construction Completed | |
Busan (Busan Technopark) |
1.3 t/day (600 Nm3/h) | May 1, 2020 - Feb. 28, 2023 (34 months) | Construction Completed | ||
Incheon (Institute for Advanced Engineering) |
1.3 t/day (600 Nm3/h) | May 1, 2020 - Feb. 28, 2023 (34 months) | Construction Completed | ||
Jeonbuk Wanju (Woosuk University Industry-Academic Cooperation Foundation) |
1.3 t/day (600 Nm3/h) | Dec. 1, 2020 - Mar. 31, 2023 (28 months) | Construction Completed | ||
Medium-to-Large Scale | 2020 |
Gyeongnam Changwon (Korea Gas Corporation) |
10.8 t/day (5,000 Nm3/h) | Jan. 1, 2020 - Dec. 31, 2023 (36 months) | Construction Completed |
Gwangju Gwangsan (Korea Gas Corporation) |
4.3 t/day (2,000 Nm3/h) | Jan. 1, 2020 - Dec. 31, 2023 (36 months) | Construction Completed | ||
2021 |
Gyeonggi Pyeongtaek (Gyeonggi Economic Science Promotion Agency) |
16.2 t/day (7,500 Nm3/h) | Jul. 1, 2021 - Jun. 30, 2023 (24 months) | Under Construction | |
Water Electro-lysis | 2022 |
Jeonbuk Buan (Jeonbuk Technopark) |
1 t/day (466 Nm3/h) | Jun. 1, 2022 - May 31, 2024 (36 months) | Under Construction |
Gangwon Pyeongchang (Korea Gas Technology Corporation) |
1 t/day (500 Nm3/h) | Oct. 1, 2022 - Sep. 30, 2024 (36 months) | Under Construction | ||
2023 |
Chungnam Boryeong (Korea Midland Power) |
1 t/day (466 Nm3/h) | Nov. 1, 2023 - Oct. 30, 2025 (36 months) | Selection completed | |
Gangwon Donghae (Korea East-West Power) |
1 t/day (466 Nm3/h) | Dec. 1, 2023 - Nov. 31, 2025 (36 months) | Selection completed | ||
Carbon Capture | 2023 |
Chungbuk Cheongju (Chungbuk Technopark) |
3 t/day (1,500 Nm3/h) | Sep. 1, 2023 - Dec. 31, 2025 (28 months) | Selection completed |
Shipping Center | 2021 |
Jeonnam Yeosu (Deokyang Energen Co., Ltd.) |
7.8 t/day 3,600 Nm3/h | Jul. 2021 - Aug. 2022 (14 months) | Construction Completed |
2022 |
Ulsan Metropolitan City (Linde Hydrogen Energy) |
15 t/day | Nov. 2022 - Dec. 2023 (14 months) | Construction Completed | |
Chungnam Seosan (Air Liquide Korea) |
15 t/day | Nov. 2022 – Dec. 2023 (14 months) | Under Construction |
Planning and discovering new infrastructure construction projects necessary for the expansion of the hydrogen economy and industrial promotion in accordance with Article 33, Paragraph 2, Clause 5 of the Hydrogen Act and Article 15, Paragraphs 3, 4, and 6 of its Enforcement Rules
② The promotion agency shall carry out the following projects.
“Projects specified by the Ordinance of the Ministry of Trade, Industry and Energy” in Article 33, Paragraph 2, Clause 5 of the Act refers to the following projects.